Planning permit timelines in Victoria, explained

You have lodged your plans with council. Now what? Here is what happens to a planning application in Victoria, how long each stage takes, and what you can do to keep it moving.

In short
  • VicSmart applications, including many two-homes-on-a-lot projects, must be decided in 10 business days.
  • Standard applications have a 60-day statutory clock, but it pauses for further information and advertising.
  • Objections and VCAT reviews are the biggest source of delay.
  • A complete application and a design that meets the rules are the best ways to save time.

Why timelines vary so much

There is no single answer to "how long does a permit take?". A straightforward application can be decided in weeks; a contested one can take more than a year. What makes the difference is which pathway your application is on, how complete it is when you lodge, and whether anyone objects.

PathwayWho it suitsDecision time
VicSmartSimple applications, including two homes on a lot that meet the rules10 business days, no neighbour notice
Townhouse and Low-Rise CodeUp to three storeys where the design meets every deemed-to-comply standardStandard clock, but no third-party appeals on those standards
Standard permitEverything else60 statutory days, plus any pauses (see below)

Statutory days are the days the council clock is running. Real-world time from lodging to permit is usually longer.

The standard permit, step by step

  1. 1Pre-application meeting1–4 weeksOptional but worth it. A council planner flags issues before you spend on full drawings.
  2. 2Lodge the applicationDay 0Plans, title, planning report and fees go in. The 60-day clock starts on a complete application.
  3. 3Request for further informationPauses clockIf council needs more, it asks early and the clock restarts once you respond. Fast, complete answers save weeks.
  4. 4ReferralsUp to 28 daysSome applications go to authorities such as Melbourne Water or VicRoads, who usually have 28 days to respond.
  5. 5Advertising2–4 weeksCouncil may require notice to neighbours: letters and a sign on site. Objections can be made for at least 14 days.
  6. 6Assessment and decisionTo day 60The planner assesses the plans against the planning scheme. Council issues a permit, a Notice of Decision, or a refusal.
  7. 7Appeal window and VCATVariesIf there are objections, objectors can ask VCAT to review a Notice of Decision; you can appeal a refusal or conditions. A VCAT review commonly adds many months.
Key point

The 60 days only counts while the clock is running. Waiting for your further information, advertising and VCAT all sit outside it, which is why most standard applications take longer in practice.

What slows an application down

  • An incomplete application. Missing reports or unclear plans trigger a request for further information and restart the clock.
  • Designs that push the rules. Going over height, coverage or setbacks invites objections and redesigns.
  • Objections from neighbours. Even a few can mean mediation, changes, or a VCAT hearing.
  • Overlays. Heritage, flooding or vegetation controls add referrals and specialist reports.
  • Council workload. Some councils are simply busier than others.

How to speed things up

  • Check early whether your project qualifies for VicSmart or the Townhouse and Low-Rise Code.
  • Book a pre-application meeting with council.
  • Lodge a complete application with every report the scheme asks for.
  • Design within the standards rather than asking for variations.
  • Talk to neighbours before you lodge; fewer surprises mean fewer objections.
  • Reply to further-information requests quickly and in full.
Watch out

A planning permit is not a building permit. Once you have planning approval, you still need a building permit from a registered building surveyor before construction starts. Permits also expire if work does not start in time, so check the conditions.

Sources and further reading
  • Planning Victoria: Faster approvals for two homes on a lot (Amendment VC288, from 16 October 2025)
  • Planning Victoria: VicSmart Planner and Practitioner Guide
  • Planning and Environment Act 1987 and Planning and Environment Regulations 2015 (statutory timeframes)
  • Your council's planning permit process page